UNIVERSAL US AND UT COMPACTORS

US 8-2

HIGH STANDARD

Narrow excavations, are a particular challenge for soil compactor design. The use of the Universal Compactor Standard (US) eliminates the need for the risky operation of a manually guided jumper. The narrow design of this manoeuvrable unit, provides optimum guidance. The special shape, guarantees compaction in hard-to-reach areas.

TECHNICAL SPECIFICATIONS:

STANDARD EQUIPMENT

RECOMMENDED EXCAVATOR SIZE IN TONSfrom 6 tons

WEIGHT WITH ROTARY MECHANISM (kg)485

BASE PLATE WIDTH X LENGTH (mm)240 x 830

HEIGHT (mm)1330

DUMPING HEIGHT / LOAD40-60 cm / 2 tons

ROTARY MECHANISMR9

WORKING STAGE X1
Oil flow [l/min]: 55-140
Operating pressure [bar]: 120-250
Centrifugal force [kN]: 12
Frequency [Hz]: 38

UT 8-2

A WELL THOUGHT-OUT TELESCOPIC SOLUTION

Great depths require special solutions. A solution of this kind is the universal telescopic compactor (UT). The telescopic upper part of this unit can be freely adapted to local building conditions. Like the standard model, the telescopic compactor guarantees safe working without danger from exhaust fumes.

SPECYFIKACJA TECHNICZNA:

STANDARD EQUIPMENT

RECOMMENDED EXCAVATOR SIZE IN TONSfrom 6 tons

WEIGHT WITH ROTARY MECHANISM (kg)630

BASE PLATE WIDTH X LENGTH (mm)240 x 830

HEIGHT (mm)1860-2360

DUMPING HEIGHT / LOAD40-60 cm / 2 tons

ROTARY MECHANISMR9

WORKING STAGE X1
Oil flow [l/min]: 55-140
Operating pressure [bar]: 120-250
Centrifugal force [kN]: 12
Frequency [Hz]: 38

HAND-COMPRESSION

Classic technique for soil compaction in the area of pipe laying using a manually guided jumper

Personnel, equipment and materials involved:

1 employee

1 excavator with operator

1 jumper 70 kg

Loose to weakly cohesive soils

Reinforced concrete pipe Ei DN 1400 / 2100

Work activities and requirements:

Layer backfilling and compaction of a 3 m section of pipe

Backfilling height 35 cm, corresponds to a layer thickness of 30 cm

Number of passes: 3 times

Number of layers: 10

Working time per layer: 9 minutes

10 layers x 9 minutes = 90 minutes

= 1.5 hours

AUTOMATISED COMPACTION

New, optimised technique for soil compaction in the pipeline laying area using the UT 8-2 universal compactor

Personnel, equipment and materials involved:

1 excavator with operator

1 MTS UT 8-2

Loose to weakly cohesive soils

Reinforced concrete pipe Ei DN 1400 / 2100

Work activities and requirements:

Layer backfilling and compaction of a 3 m section of pipe

Backfill height 50 cm, corresponds to a layer thickness of 43 cm

Number of passes: 2 times

Number of layers: 7

Working time per layer: 3 minutes

7 layers x 3 minutes = 21 minutes

= 0.35 hours

SEE HOW IT WORKS: